標題Title: Why are the lead times so long
作者Authors: Sandrine
上傳單位Department: 管理與資訊系
上傳時間Date: 2014-11-21
上傳者Author: 張嘉華
審核單位Department: 管理與資訊系
審核老師Teacher: 張嘉華
檔案類型Categories: 研究生論文報告Thesis
關鍵詞Keyword: SCM
摘要Abstract: The main reason for the lead times to be so long in H. C. Starck, Incorporated, is the
inaccurate scheduling made by operators. The company uses SAP R/3, an Enterprise Resource
Planning software, for recording all accounting transactions (order creation and all material
movements) but not for scheduling and production planning, unfortunately. Production planning is
still done manually, as well as raw material ordering and shop floor scheduling. Employees use paperbased
process to transmit the sales orders of customers to the operations department (where the
products start to be manufactured). These tasks, done manually, take more time than using a
software to accomplish them, which causes the lead times to be so long. The company didn’t make
full use of the functions in SAP R/3. In fact, schedule misses were mostly due to equipment failure.